GRP: |
San Juan Islands and North Puget Sound
|
Strategy Area: |
Eagle Harbor (Northeast Side of Cypress Island) SK
|
Strategy Number: |
NPS-76
|
Checked By: |
Ken Schacht
|
Date: |
1/20/2006
|
Type: |
Field Test
|
Latitude: |
Same as in GRP booklet March 2003
|
Longitude: |
Same as in GRP booklet March 2003
|
Location: |
Cypress Island, Eagle Harbor
|
Response Strategy: |
exclusion booming
|
Feet/Type of Boom: |
1300'
|
Strategy Implementation: |
Same as in GRP booklet March 2003. 1300' feet of boom is the proper amount to complete GRP. On the east bluff an attachment point would be very helpful. Anchoring boom would leave gap between rock wall and end of boom.
|
Staging Area: |
Same as in GRP booklet March 2003
|
Site Access: |
Same as in GRP booklet March 2003
|
Resources Requiring Protection: |
Same as in GRP booklet March 2003
|
Comments: |
|